epic(lab): home lab build-out — racking, switches, edge routing, mesh Wi-Fi, cluster bring-up (tracking) #6066

Open

Description

@dezren39

Drew's home lab build-out story (2026-11-04 ~23:30 CST), filed as a ticket set. These are Drew's hands-on physical tasks — the tickets structure his work; any config/doc prep named in a ticket is agent work.

Proposed sequence

Physical plant first, then switches, then routing/mesh on top of the plant, then interconnect, then the cluster on a stable network:

  1. Racking + units placed
  2. Dell switches (×3) — each: rails → firmware → verify → initial config → config stored → labels
  3. Edge routing + mesh
  4. Cluster interconnect
  5. Cluster bring-up — TALM + Talos + Cozystack: already ticketed as epic(cluster): TALM + Talos bootstrap #1086 (TALM + Talos bootstrap) and epic(cluster): Cozystack platform #1087 (Cozystack platform) under program epic EPIC: Basement Talos/Cozystack cluster program #1817; no new ticket filed (cross-link comment on epic(cluster): TALM + Talos bootstrap #1086). This is also the execution home for the tracked goal "Stand up lab cluster (talm, talos, cozystack, postgres, rustfs)" (goal_ba17a5777c21).
  6. Generic containers for ID + fleet — software-side, can be prepared in parallel; deployed once network/cluster are ready

Side research (no sequence dependency):

Notes

Activity

  1. added
    kind/choreRoutine maintenance, housekeeping, dependency hygiene
    area/infraInfrastructure, deployment, and operations
    on Nov 5, 2026
  2. developing-today commented on Nov 5, 2026

    @developing-today
    Contributor
  3. dezren39 commented on Nov 5, 2026

    @dezren39
    MemberAuthor

    Power dependency for this build-out set: #1105 (task(cluster): install and verify the dedicated 20A circuits, under the basement power epic #1083) — scope updated 2026-11-04 with panel review, wiring check, and 4–16 dedicated 20A circuits (count decided by the panel review + full-build-out load calc). Heavy racking (#6070) and the switch installs (#6073/#6074/#6075) sequence after or alongside the electrical work; the interconnect/cluster bring-up assumes the circuits it plugs into exist. Circuit → load mapping will be recorded on #1105 as circuits land.

  4. added
    queue/queuedHas a queued task in the Supabase agent queue
    task/triageQueue packet kind: verify, reproduce, and route this item
    work/assignedQueue worker lifecycle state
    queue/claimedQueue worker lifecycle state
    and removed
    queue/queuedHas a queued task in the Supabase agent queue
    on Nov 5, 2026
  5. dezren39 commented on Nov 5, 2026

    @dezren39
    MemberAuthor

    🤖 Agent note · done (triage)

    Triage findings (verified fresh 2026-11-05 via gh):

    Triage complete for task 10429; issue #6066 stays open as the tracking epic.

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Metadata

Metadata

Assignees

Labels

area/infraInfrastructure, deployment, and operationskind/choreRoutine maintenance, housekeeping, dependency hygienetask/triageQueue packet kind: verify, reproduce, and route this item

Type

No type

Projects

No projects

    Milestone

    No milestone

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions